Aerators Tracker

Aerators Tracker

From delivery to live power connection, tracked in public.

Total units16
Delivered13/16
Mountings planned2
In water now0
On diesel now0
On grid now0

Stage Pipeline

Delivered to Site13/16
81.3%
Mountings Planned2/16
12.5%
Mountings Complete0/2
0.0%
In Water (Actual)0/2
0.0%
Diesel Gensets Onsite0/2
0.0%
Running on Diesel0/2
0.0%
Running on Grid Power0/16
0.0%

Current Reality

  • 13 of 16 aerators delivered to site.
  • First 2 mountings are planned, but not installed yet.
  • First 2 are planned for water install, currently 0 in water.
  • No diesel gensets onsite yet, so 0 on diesel power.
  • Network power stage still pending, with transformer details to be confirmed.

Council Schedule Window

Approved by Council: 2 Apr 2026 (Newsline).

Expected operation window: within 6-10 weeks.

10-week target date: 11 Jun 2026 (43 days remaining).

Days since the 29 Jan 2026 big stink - 90

Latest snapshot: 27 Apr 2026 (Monday)

Baseline: 13 of 16 delivered. First 2 mountings planned. First 2 planned for water install. No gensets onsite yet.

Live Progress Tracking

See exactly how many aerator stages are completed in real time.

Performance Insights

Compare stage progress and identify where delivery slows.

Forecast Completion

Track rollout against the Council-approved timeline window.

Ahead or Behind Schedule

Know instantly if implementation is tracking to plan.

Accountability & Transparency

Hold this programme to account with clear public reporting.

Built for the Community

Because Christchurch deserves clear, honest progress updates.

Watch it. Track it. Hold them to account sewercrisis.nz