Aerators Tracker
From delivery to live power connection, tracked in public.
Total units16
Delivered16/16
Mountings planned2
In water now0
On diesel now0
On grid now0
Stage Pipeline
Delivered to Site16/16
100.0%
Path Clearing Underway0/1
0.0%
Pipes Majority Arrived0/1
0.0%
Construction Village Ready0/1
0.0%
Mountings Planned2/16
12.5%
Mountings Complete0/2
0.0%
In Water (Actual)0/2
0.0%
Diesel Gensets Onsite0/2
0.0%
Running on Diesel0/2
0.0%
Running on Grid Power0/16
0.0%
Current Reality
- All aerators are now delivered to site.
- Path clearing works are underway to improve access for prep and cabling.
- Majority of required pipes have arrived on site for upcoming installation.
- Construction village is fully set up, supporting faster site delivery.
- First 2 mountings are planned, but not installed yet.
- First 2 are planned for water install, currently 0 in water.
- No diesel gensets onsite yet, so 0 on diesel power right now.
- Network power stage still pending, with transformer details to be confirmed.
Council Schedule Window
Approved by Council: 2 Apr 2026 (Newsline).
Expected operation window: within 6-10 weeks.
10-week target date: 11 Jun 2026 (23 days remaining).
Days since the 29 Jan 2026 big stink - 110
Progress Highlights
- All aerators delivered to site.
- Path clearing underway for access and cable route prep.
- Majority of pipes now on site for installation phase.
- Construction village fully set up for delivery teams.
- CCC update notes pond conditions remain stable through seasonal transition.
- Council-approved aerator operation window remains 6-10 weeks from approval date.
Latest snapshot: 1 May 2026 (Friday)
Baseline: 13 of 16 delivered. First 2 mountings planned. First 2 planned for water install. No gensets onsite yet.
Live Progress Tracking
See exactly how many aerator stages are completed in real time.
Performance Insights
Compare stage progress and identify where delivery slows.
Forecast Completion
Track rollout against the Council-approved timeline window.
Ahead or Behind Schedule
Know instantly if implementation is tracking to plan.
Accountability & Transparency
Hold this programme to account with clear public reporting.
Built for the Community
Because Christchurch deserves clear, honest progress updates.
Watch it. Track it. Hold them to account sewercrisis.nz