Aerators Tracker
From delivery to live power connection, tracked in public.
Total units16
Delivered13/16
Mountings planned2
In water now0
On diesel now0
On grid now0
Stage Pipeline
Delivered to Site13/16
81.3%
Mountings Planned2/16
12.5%
Mountings Complete0/2
0.0%
In Water (Actual)0/2
0.0%
Diesel Gensets Onsite0/2
0.0%
Running on Diesel0/2
0.0%
Running on Grid Power0/16
0.0%
Current Reality
- 13 of 16 aerators delivered to site.
- First 2 mountings are planned, but not installed yet.
- First 2 are planned for water install, currently 0 in water.
- No diesel gensets onsite yet, so 0 on diesel power.
- Network power stage still pending, with transformer details to be confirmed.
Council Schedule Window
Approved by Council: 2 Apr 2026 (Newsline).
Expected operation window: within 6-10 weeks.
10-week target date: 11 Jun 2026 (43 days remaining).
Days since the 29 Jan 2026 big stink - 90
Latest snapshot: 27 Apr 2026 (Monday)
Baseline: 13 of 16 delivered. First 2 mountings planned. First 2 planned for water install. No gensets onsite yet.
Live Progress Tracking
See exactly how many aerator stages are completed in real time.
Performance Insights
Compare stage progress and identify where delivery slows.
Forecast Completion
Track rollout against the Council-approved timeline window.
Ahead or Behind Schedule
Know instantly if implementation is tracking to plan.
Accountability & Transparency
Hold this programme to account with clear public reporting.
Built for the Community
Because Christchurch deserves clear, honest progress updates.
Watch it. Track it. Hold them to account sewercrisis.nz