Stone Columns Tracker

Stone Columns Tracker

Transparency. Accountability. No more secrets.

Progress to Date

1,600 target

550 installed

34.4% complete

Started: Mon 20 Apr 2026

Performance: Actual vs Required

0 400 800 1,200 1,600 20 Apr 25 Jun 31 Aug
Average rate (all days)22.9/day
Average rate (last 5 days)32.3/day
Required rate9.6/day
Days remaining109
Ahead of Schedule You are 261 columns ahead of the required pace.

Latest Update

Latest Update

  • Date: 14 May 2026 (Thursday)
  • Total installed: 550
  • Added today: 258
  • Forecast completion: 16 Jun 2026

Live Progress Tracking

See exactly how many stone columns are installed in real time.

Performance Insights

Compare actual progress against required pace and trend.

Forecast Completion

Estimate completion date based on current install rates.

Ahead or Behind Schedule

Know instantly if the project is on track to finish on time.

Accountability & Transparency

Hold the project to account with clear public data.

Built for the Community

Because Christchurch deserves better.

Watch it. Track it. Hold them to account sewercrisis.nz