Stone Columns Tracker
Transparency. Accountability. No more secrets.
Progress to Date
1,600 target
550 installed
34.4% complete
Started: Mon 20 Apr 2026
Performance: Actual vs Required
Average rate (all days)22.9/day
Average rate (last 5 days)32.3/day
Required rate9.6/day
Days remaining109
Ahead of Schedule
You are 261 columns ahead of the required pace.
Latest Update
Latest Update
- Date: 14 May 2026 (Thursday)
- Total installed: 550
- Added today: 258
- Forecast completion: 16 Jun 2026
Live Progress Tracking
See exactly how many stone columns are installed in real time.
Performance Insights
Compare actual progress against required pace and trend.
Forecast Completion
Estimate completion date based on current install rates.
Ahead or Behind Schedule
Know instantly if the project is on track to finish on time.
Accountability & Transparency
Hold the project to account with clear public data.
Built for the Community
Because Christchurch deserves better.
Watch it. Track it. Hold them to account sewercrisis.nz